Our man hours calculator is a vital tool in project management and workforce planning, it helps estimate the total amount of labor required to complete a specific task or project.
A construction project where a team of 5 workers needs to build a wall, if each worker spends 8 hours daily for 3 days, the total man-hours would be:
5 workers × 8 hours × 3 days = 120 man-hours
Man-Hours Calculator
Project Type | Workers | Hours/Day | Days | Total Man-Hours |
---|---|---|---|---|
Website Design | 3 | 6 | 15 | 270 |
Home Renovation | 5 | 8 | 10 | 400 |
Event Planning | 4 | 7 | 7 | 196 |
Data Analysis | 2 | 9 | 5 | 90 |
Product Launch | 6 | 10 | 3 | 180 |
Marketing Campaign | 4 | 5 | 20 | 400 |
Software Testing | 5 | 8 | 12 | 480 |
Construction Project | 10 | 8 | 30 | 2,400 |
Research Study | 3 | 4 | 25 | 300 |
Training Program | 8 | 6 | 10 | 480 |
Graphic Design Project | 2 | 7 | 14 | 196 |
Community Outreach | 6 | 5 | 15 | 450 |
IT Support | 4 | 8 | 22 | 704 |
New Product Development | 7 | 9 | 18 | 1,134 |
Facility Maintenance | 3 | 4 | 30 | 360 |
Man-Hours Calculation Formula
The formula for calculating man-hours is:
Man-hours = Number of workers × Hours worked per worker
This formula can be expanded to accommodate various scenarios:
- For a single task: Man-hours = Number of workers × Time spent by each worker
- For multiple tasks: Sum of (Number of workers × Time spent by each worker) for each task
- For a project duration: Man-hours = Number of workers × Hours per day × Number of working days
A software development project requires:
3 developers working 6 hours daily for 10 days
2 designers working 4 hours daily for 5 days
1 project manager working 8 hours daily for 15 days
Total man-hours = (3 × 6 × 10) + (2 × 4 × 5) + (1 × 8 × 15) = 180 + 40 + 120 = 340 man-hours
How to Calculate Man-Hours per Month
To calculate man-hours per month, consider the:
- Number of working days in the month
- Number of employees
- Hours worked per day
Formula: Monthly man-hours = Number of employees × Working days × Hours per day
A company has 25 employees working 8 hours a day, and there are 22 working days in a month.
Monthly man-hours = 25 × 22 × 8 = 4,400 man-hours
This calculation helps in long-term planning and assessing overall workforce productivity.
What Does 2.5 Man-Hours Mean?
The term “2.5 man-hours” represents the amount of work that can be completed by one person in 2.5 hours, or by multiple people whose combined work time equals 2.5 hours.
For instance:
- One person working for 2 hours and 30 minutes
- Two people working for 1 hour and 15 minutes each
- Five people working for 30 minutes each
How to Calculate Safe Man-Hours
Formula: Safe man-hours = Total man-hours worked – Man-hours lost due to injuries
A factory with 100 workers operates for 250 days, working 8 hours per day. There was one incident resulting in 16 hours of lost time.
Total man-hours = 100 × 250 × 8 = 200,000 hours
Safe man-hours = 200,000 - 16 = 199,984 hours
Safe man-hours refer to the cumulative number of hours worked without a lost-time injury. This metric is crucial for assessing workplace safety and promoting a safety-first culture.
How are OSHA Man-Hours Calculated?
OSHA Formula: Total OSHA recordable cases × 200,000 / Total man-hours worked
The factor 200,000 represents 100 employees working 40 hours per week for 50 weeks per year.
The Occupational Safety and Health Administration (OSHA) uses man-hours to calculate incident rates. OSHA man-hours include all hours worked by full-time, part-time, and seasonal workers, including overtime.
A company with 500 employees working 2,000 hours each per year experiences 10 recordable incidents.
Total man-hours = 500 × 2,000 = 1,000,000
OSHA Incident Rate = (10 × 200,000) / 1,000,000 = 2.0
This rate indicates 2 incidents per 100 full-time workers annually, providing a standardized measure for comparing safety performance across different company sizes and industries.
Sources / References
- Project Management Institute: https://www.pmi.org/
- Occupational Safety and Health Administration: https://www.osha.gov/
- Bureau of Labor Statistics: https://www.bls.gov/
Related Tools: